You told yourself the report would take an afternoon. By the time the light changes outside the window, you are on page two of five, and tomorrow’s plan quietly absorbs today’s. The estimate felt reasonable when you made it, and the same thing happened the last time. That pattern has a name, the planning fallacy, and it has been measured in student theses, computer assignments and national construction projects.
Key Takeaways
- The planning fallacy is the tendency to hold a confident belief that one’s own project will proceed as planned while knowing that most similar projects have run late, a pattern termed the planning fallacy by Kahneman and Tversky (1979) and described this way in Buehler et al. (1994).
- In Buehler, Griffin and Ross’s first study, 37 psychology honors thesis students at the University of Waterloo predicted they would finish in 33.9 days on average and actually took 55.5 days; 29.7 percent finished within their predicted time (Buehler et al., 1994).
- Even the “everything goes as poorly as it possibly could” forecast came in under reality: 48.6 predicted days against 55.5 actual, with 48.7 percent of students finishing by that date (Buehler et al., 1994).
- In a 123-student study, those asked to link past experiences to the current task finished at their predicted time 60.0 percent of the time, against 29.3 percent in the control group (Buehler et al., 1994).
- Reference-class forecasting, described by Flyvbjerg (2006), bases a forecast on the actual outcomes of a class of comparable past projects.
What is the planning fallacy?
The planning fallacy is the tendency to underestimate how long a task will take, even when past similar tasks ran over. Buehler, Griffin and Ross (1994) describe it as the tendency to hold a confident belief that one’s own project will proceed as planned, even while knowing that the vast majority of similar projects have run late.
They credit the term to Kahneman and Tversky (1979), in a chapter titled “Intuitive Prediction: Biases and Corrective Procedures” in TIMS Studies in Management Science.
Where do planning fallacy examples come from?
The 1994 paper opens with three large public projects, each described there from the historical record:
- The transcontinental railway. In 1871, British Columbia agreed to join Canada on the condition that a railway reach the west coast by 1881. The last spike was driven in 1885.
- Montreal’s Olympic stadium. In 1969 the mayor announced that the 1976 Olympics, including a stadium with a retractable roof, would cost $120 million in all. The roof was in place in 1989 and cost $120 million by itself.
- The Sydney Opera House. The 1957 estimate was completion in early 1963 for $7 million. A scaled-down version opened in 1973 at a cost of $102 million.
Buehler and colleagues use these cases to show that the pattern predates the laboratory. Their own studies then bring it down to the scale of a single person’s week.
What did the 1994 thesis study find?
The first study in Buehler, Griffin and Ross (1994) took 37 psychology students (27 women and 10 men) in the final semester of the Honors Thesis course at the University of Waterloo. A researcher phoned each student near the end of the project and asked when the thesis would be submitted. The course coordinator recorded the actual submission date.
Each student gave three predictions. The results, for the 33 students who had finished when records closed:
- Best estimate: 33.9 days predicted, 55.5 days actual. 29.7 percent finished in the time they predicted.
- Everything goes as well as it possibly could: 27.4 days predicted. 10.8 percent finished by that date.
- Everything goes as poorly as it possibly could: 48.6 days predicted. 48.7 percent finished by that date.
Four further students had not finished two semesters after the survey and were left out of this analysis.
The authors also report that predicted and actual completion times were highly correlated (r = .77). Students who predicted a longer time did take longer. The forecasts carried real information, and the whole set sat below the actual times.
Does the planning fallacy appear in everyday tasks?
The same paper reports further studies with undergraduate psychology students, and in each of them fewer than half of the participants finished in the time they originally predicted.
- Study 2 (104 students): students described one school project and one non-school project they planned to finish within a week. They finished 37.1 percent of the academic projects and 42.5 percent of the nonacademic projects within the predicted time.
- Study 3 (78 students): students described a school project due within two weeks, and a follow-up interview came a week after the deadline. 43.6 percent of the students finished within the predicted time.
- Study 4 (123 students): the task was a computer tutorial assignment that took about an hour. Control participants predicted 5.5 days and took 6.8.
The authors summarise the size of the miss as ranging from about one day in Studies 3 and 4 to several weeks in Study 1.
What are people thinking when they predict?
In Study 3, participants thought aloud while forecasting, and the recordings were transcribed. Buehler and colleagues report that participants constructed narratives of how the future would unfold, often with detailed plans for completing the task. Participants rarely considered their own past experiences with similar tasks. When they did describe the past, they usually chose occasions that justified their optimism.
Study 4 repeated the pattern in numbers. Of the participants, 93.5 percent reported considering future plans and scenarios, and 8.9 percent reported thinking about past experiences. Most of the plans described how the project would be completed successfully, and 9.8 percent mentioned future impediments.
Kahneman and Tversky’s account, as Buehler and colleagues summarise it, distinguishes two kinds of information:
- Singular information concerns aspects of the specific task that might lengthen or shorten it. Using it is the inside view: working out how this task will get done.
- Distributional information concerns how long other, similar tasks took. Using it is the outside view: comparing the present task with past projects.
The planning fallacy, in this account, is a pattern of forecasting from the inside view.
Why do tasks take longer than planned?
The 2010 review by Buehler, Griffin and Peetz, published in Advances in Experimental Social Psychology, defines the planning fallacy and surveys the research on its scope and generality. It traces the origins starting from the Kahneman and Tversky inside-outside model, then proposes an extended model that combines cognitive, motivational, social and behavioral explanations.
The 1994 studies offer three findings that fit a plain reading of “why”:
- Plans take the lead. Forecasts were built from plan-based scenarios, and past experience played a small part in them.
- Past misses get explained away. In Studies 3 and 4, participants attributed their earlier prediction failures to relatively external, transient and specific factors, which leaves the past looking irrelevant to the present task.
- Deadlines frame the forecast. Participants in the experiments always predicted they would finish before their deadline.
The paper also names a separate source of optimism in large public projects: proponents may deliberately provide overly optimistic assessments of cost and time to win approval. Flyvbjerg (2006) explains forecast inaccuracy as a combination of optimism bias and strategic misrepresentation.
What does the outside view look like?
Flyvbjerg (2006) presents reference-class forecasting as a method for debiasing forecasts by taking an outside view, and lays it out in three steps:
- Identify a relevant reference class of past, similar projects, broad enough to be statistically meaningful and narrow enough to be truly comparable.
- Establish a probability distribution for that class, from credible empirical data.
- Compare the specific project with the distribution to find its most likely outcome.
Flyvbjerg retells a story from Daniel Kahneman about a curriculum project in Israel. The team’s own estimates ranged from 18 to 30 months. When a curriculum expert on the team was asked how long comparable teams had taken, he recalled that about 40 percent never finished, and that none of the others took less than seven years or more than ten. The team went ahead and completed the project eight years later.
The two forecasts came from the same expert about the same project. The first looked at the team’s plan and resources. The second looked at the record of similar teams.
Can people be trained to use the past?
Study 4 tested a version of the outside view at the scale of a personal assignment. There were three conditions:
- Control: participants predicted, then described past experiences afterward.
- Recall: participants described past experiences with similar assignments just before predicting.
- Recall-relevant: participants described past experiences, then stated when they would finish if they completed the assignment as far ahead of the deadline as they typically did, and wrote a plausible scenario, based on past experience, that would lead to finishing at their typical time.
The results for the 123 participants:
- Predicted and actual days, control: 5.5 predicted, 6.8 actual, 29.3 percent finished in the predicted time.
- Predicted and actual days, recall: 5.3 predicted, 6.3 actual, 38.1 percent finished in the predicted time.
- Predicted and actual days, recall-relevant: 7.0 predicted, 7.0 actual, 60.0 percent finished in the predicted time.
The manipulation changed predictions without changing behaviour: actual completion times did not differ among the three conditions. The authors conclude that the optimistic bias was eliminated for participants who connected relevant past experiences with their predictions.
Study 5 turned the lens outward. Observers who predicted when another student would finish gave longer forecasts than the students themselves, 8.5 days against 5.5 days, and they overestimated the completion times.
Where does the evidence stop?
The experimental evidence above comes from undergraduate psychology students working on assignments, and one study with honors thesis students. The tasks ran from an hour of tutorial to a semester-long project.
Reference-class forecasting has its own evidence base in project management, where Flyvbjerg (2006) reports the first practical application, to cost forecasts for large transportation infrastructure projects. Buehler and colleagues describe several open questions in their own paper, including the role of motivation and the consequences of optimistic time estimates, and the 2010 review continues that work.
That leaves a modest toolkit, grounded in clear findings from specific settings. It suggests a few practical moves for a personal to-do list, offered here as applications of the research:
- Look up your own record. Pull three similar past tasks and note how long each took.
- Write the typical finish time next to the plan. The recall-relevant condition asked for exactly this kind of link between past and present.
- Time-box a first block. A fixed session, as in the pomodoro technique, produces a fresh data point on how long a piece of work takes.
Underestimated time also feeds the procrastination cycle: a plan that looked easy on Monday becomes a backlog by Thursday. For the wider picture of why people delay, see why we procrastinate and overcoming procrastination.
What does an honest estimate sound like?
An honest estimate is a sentence that includes the past. “The last three reports took about two afternoons each, so this one probably takes two.”
There is a quiet kindness in it. The plan you wrote at the start of the week gets to be a hope, and the number next to it gets to be a record. The next time you size up a task, you might ask what the last three did.
Related reading
- ADHD Procrastination: Why Your Brain Works Differently
- Bedtime Procrastination Statistics: How Common Going to Bed Late Really Is
- Chronic Procrastination: When Delay Becomes a Way of Life
References
Buehler, R., Griffin, D., & Peetz, J. (2010). The planning fallacy: Cognitive, motivational, and social origins. Advances in Experimental Social Psychology, 43, 1-62.
Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the “planning fallacy”: Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381.
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15.
Kahneman, D., & Tversky, A. (1979). Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313-327.